Subject: Contract No. W912DR-10-C-0094; Utah Data Center, Camp Williams. Utah
31 - Data Halls; C-Coded Submittals
Balfour Beatty/DPRyBig-D
404 West 400 South
Salt Lake City, Utah 84101-1108
Gentlemen,
This letter is in regards to submittals returned to the Contractor with a C-code. As per
RFP Section 01 33 00.05 20, paragraph 1.4.2.1 Scheduling of Government Approved
Submittals. "The Contractor shall resubmit rejected submittals within 14 days of receipt
of the rejection". Therefore, construction submittals returned to the Contractor with a C-
code will be E-coded if not resubmitted with the appropriate revisions or additions after
14 days.
The following construction submittals returned to BDB with a C-code, have not been
resubmitted within 14 days, and will therefore be E-coded.
0341 33 1. 14.7SD-04 Structural Precast MockupPhotos-returned 5/9/11.
05 12 00 1 .6.1 SD-02 Tunnel Trench Steel Fab Drwgs{IFC) - returned 5/27/1 1 .
22 00 00 UG Plumbing System Shop Drawings - returned 5/27/1 1 .
As per Serial Letter C-0172 dated May 26, 2011;
“IftheASI is found acceptable after the 14-day review period, it will be C-coded.
Once any comments are incorporated and BDB issues the ASI in accordance
with the IFC distribution, the ASI will be A-coded."
ASI's will not be E-coded similar to construction submittals after 14 days. However,
Notice to Proceed for the portion of the work covered by the ASI will not be issued until
the ASI is A-coded or B-coded.
Please (801) 302-5031, if you have any comments or
questions regarding this letter.
CPT, EN, USAR
Contracting Officer's Representative
Wiliams Resident Office